A quick Visit of the CEO to the projects of Annaba and Skikda
While the CEO was in the East, accompanied by the Director of Works, he had the opportunity to see very closely the progress of works at two projects that are building the Annaba Power Plant and the realization of the Skikda mégatrain.
Indeed, wanting to inquire about the progress of work, the CEO conducted a very short visit at the site, where he received clarification on the causes of delay in setting piles at the project Annaba Port for the General Electric.
Concerning the construction of the project Mégatrain (SP1) at Skikda, launched on the 7th November 2007 in collaboration with KBR, it is noted a substantial progress realized in conformity with forecasts.